Decommissioning of Brenillis Nuclear Power Plant
|
Client :
|
CEA (French Atomic Energy Authority) and EDF (French Utility)
|
|
Type of contract :
|
TURNKEY
|
|
Contract value :
|
15 million € (Euros)
|
-
Context
-
Framatome role
-
Project description
1. Context
In 1970 the French government chose Pressurised Water Reactor technology for its civil
nuclear park and as a consequence stopped the development of Gas Cooled Reactor
technologies.
For this reason Brennilis Nuclear Power Station, a 250 MWt heavy water moderated
reactor was shut down in 1985 after 18 years of commercial operation. Decommissioning
of the station started shortly afterwards with the removal and evacuation of the fuel,
solid waste and liquid effluent.
In 1995 the Government gave the go-ahead to complete Level 3 (Stage 3 following the
IAEA guidance) decommissioning of all buildings and facilities on the site with the
exception of the reactor building.
Two consortiums were awarded work worth a total of 200 million French Francs. Nuclear
management was awarded to a Framatome-Anp-Anp led consortium and the dismantling operations to
another consortium. The overall project management was led by EDF. The project
commenced in 1996 and is expected to finish in 1999.
2. Framatome-Anp role
Framatome-Anp associated with its subsidiary STMI undertake radiological survey and waste
inventory of the facilities to be dismantled, the design, supply and operation of waste
characterisation facilities, the supply of waste containers as well as health physics
monitoring of the 150 site personnel involved.
3. Project description
The project consists of 4 distinct phases :
1. Design studies 1996
A complete radiological survey was performed consisting of 5000 contamination and
radiation measurements including cored samples to determine an activity spectrum for
each building.
This data was used to establish an overall expected waste inventory to determine the
dismantling methodology, the type and number of waste containers required as well as
the design of radiological measurement facilities for waste packages of varying
geometry.
Some 150 m3 of contaminated concrete and 3,200 tonnes of metallic
waste will have to be packaged in 7,000 X 200 litre drums,
150 X 5 m3 containers, 450 X 7 m3
containers as well as 350 twenty foot containers.
The activity range of the waste is 1 Bq/g to a few MBq/g. A further
13,000 m3 of uncontaminated concrete will be used to backfill the
site.
2. Supply and commissioning 1997
Two waste package characterisation systems for 200 litre drums and a system for
5 m3 and 7 m3 containers have been designed, supplied
and commissioned. Waste package activities are calculated from dose rate measurements.
The drum systems have a throughput of 16 drums/day whereas the container system has a
throughput of 6 containers/day.
A computer network system has been installed which collects all data and provides
complete tracability of the waste packages in real time through the use of code bar
labelling.
Health physics management of the personnel is performed by a computer network system
which has also been commissioned. This system closely follows the personnel dose
up-take task by task, building by building and for the whole site, and comparing the
results with strict ALARA based previsions, enables interventions to be controlled or
adapted accordingly.
As part of the system a large range of personal and general surveillance health
physics equipment has been set-up on site.
3. Dismantling operations 1997 - 2003
Dismantling operations are newly underway and Framatome-Anp will ensure the provision of
all waste packages, operation of the waste characterisation equipment and management of
the waste, health physics monitoring of all personnel and management of dose
up-take.
4. Preparation for Level 3 decommissioning of the reactor
building 1999
Framatome-Anp will design, supply and commission an automatic health physics monitoring and
surveillance system for care and maintenance of the reactor building.
This new system which will replace an existing out-dated system and once installed will
enable personnel to follow the radiological evolution of every room within the building
without having to intervene.
A comprehensive radiological data base of the building will be created over time to
enable preparations for Level 3 dismantling work to begin.
|